Double Burner Incinerator

Incinerator Cap. 9 kg/batch

Jual Incinerator MKV01DB R 300x296 - Double Burner Incinerator

Spesifikasi :
Incinerator Cap. 9 kg/batch Cerobong 4 Meter
Incinerator Double Burner
Jumlah Burner : 2 unit
Kapasitas up to 5kg / batch
Ukuran Primary Chamber dia 76 x 100 cm
Ukuran secondary Chamber dia 40 x 70 cm
Diameter cerobong 40 cm/20cm
Bahan Bakar : Solar
Temperature 1st Burner : 400 – 800 Deg C , Tergantung kalori
Temperature 1st Burner : 600 – 1100 Deg C
Tinggi Cerobong dari tanah : 4 m, bisa extend
Dilengkapi water scrubber
Wall insulation : Castable
Panel : Electrical Panel, temp conntroller


Incinerator Cap. 5 kg/batch

Jual Incinerator MKV02DB R 175x300 - Double Burner Incinerator

Spesifikasi :
Incinerator Cap. 5 kg/batch Cerobong 4 Meter
Incinerator Double Burner
Jumlah Burner : 2 unit
Kapasitas up to 5kg / batch
Ukuran Incinerator Chamber 75 x 120 cm
Diameter cerobong 40 cm/25cm
Bahan Bakar : Gas atau bisa Solar (harus dipilih)
Temperature 1st Burner : 400 – 800 Deg C , Tergantung kalori
Temperature 1st Burner : 600 – 1100 Deg C
Tinggi Cerobong dari tanah : 4 m, bisa extend
Dilengkapi water scrubber
Wall insulation : Castable, Fire Brick dan Insulation Brick
Panel : Electrical Panel, temp conntroller


Incinerator Cap. 9 kg/batch
Double Burner with Scrubber (Sekitar 75 kg/hari atau Lebih)

Jual Incinerator MKV03DB R 195x300 - Double Burner IncineratorJual Incinerator MKV04DB R 136x300 - Double Burner Incinerator

Spesifikasi :
Incinerator Cap. 9 kg/batch Cerobong 8 Meter
Incinerator Cap. 9 kg/batch Cerobong 14 Meter
Type of Waste : Bulk Density :± 0.1 – 0.15 kg/m³
Incinerator Type : Domestic Waste / Sampah Bukan B3
Incinerator Capacity : 60 Liter = 9 kg/batch Multiple Chamber
Operation Time : 8 hour/day

Chamber Volume :
– 1st Chamber : 0.2 m³ ( 55 cm x 55 cm x 70 cm)
– Second chamber : 0.1 m³ ( L. 31 cm x W. 55 cm x. H.70 cm)
Incinerator Dimension (Outter) : LxWxH : 129 x 86 x 85 cm

Burner :
-1st Burner : 4 – 6 liter / hour, Light Oil Burner, Qty : 1 unit
-2nd Burner : 4 – 6 liter / hour, Light Oil Burner, Qty : 1 unit
Motor 220V / 50 Hz/ 1 Phase: 150 Watt x 2 : 300 Watt
Chamber Temperature :
-1st Chamber : 600 – 800°C
-2nd Chamber : 800- 1000°C
Chamber Pressure : Negatif (Under Atmosferic Pressure)

Exaust Stack :
-Diameter : 400mm (1st Stack), Ø200 mm (2nd Stack)
-Height : ±8 m.from ground level
-Sampling Port Ø3”
-Coating : High Temp.Paint

Insulation and Refractory Construction Materials :
-Fire Brick : Fire Brick SK 34
-Castable : CAJ-14
-Ceramic Fibre, 128 kg/m³
-Rockwool,60 kg/m³
-Glaswool, 20 kg/m³
-Bottom : Insulating Brick

Shell & Structure Material Chamber :
-Shell Plate thickness 3 mm ,Mild Steel
-Joint Flange thickness 10 mm
-Burner Port thickness 6 mm
-Plenum Plate thickness 3 mm
-Structure UNP 80 & UNP 50
-Lifter thickness 12 mm
-Coating : Epoxy Paint

FDF Blower : Sentrifugal 3″, 370 Watt , 3000 rpm, 1 unit

Diesel Oil Fuel Consumption : average12 liter / hour

Fuel Tank :
-Tank Capacity 150 ltr
-Material Tank : Mild Steel plate t. 4 mm
-Level Control
-Drain Port

Water Scrubber : Pump, Piping with Water Tank
Maximum Capacity 190 liter/min
Electricity 220 Volt, 50 Hz, 1 Phase, 370 Watt

Power Requirement : 1,2 kW / 220 Volt / 1phase / 50Hz

Control System :
-ELC
-Temperature Control : Digital
-Thermocouple : Type – K.
-Limit Switch

Ash : 5 – 10 % waste weight
Ash Discharging : Manual
Feeding System : Manual
Warranty Term : Six month ( Service)
Operator Requirement : 1 Person
Area Requirement : 3.5 x 4.5 m

Emission Quality According to Government Regulation for the
following :
-Smokeless
-CO < 100 mg/Nm3
-NO2 < 300 mg/Nm3
-Opacity < 10%


Incinerator Cap.15 kg/batch
Double Burner with Scrubber (Sekitar 120 kg/hari atau Lebih)

Jual Incinerator MKV03DB R 195x300 - Double Burner IncineratorJual Incinerator MKV04DB R 136x300 - Double Burner Incinerator

Spesifikasi :
Incinerator Cap.15 kg/batch Cerobong 8 meter
Incinerator Cap.15 kg/batch Cerobong 14 meter

Incinerator Type : Domesti Waste / Sampah Bukan B3
Incinerator Capacity : 105 Liter = 15 kg/batch Multiple Chamber
Operation Time : 8 hour/day

Chamber Volume :
-1st Chamber : 0.35 m³
-Mixing Room : 0.1 m³
-Second Chamber : 0.15 m³
Incinerator Dimension (Outter) : L:142 X W:99 X H:98 cm

Burner :
-1st Burner : 5 – 10 liter / hour, Light Oil Burner, Qty : 1 unit
-2nd Burner : 5 –10 liter / hour, Light Oil Burner, Qty : 1 unit
Motor 220V / 50 Hz/ 1 Phase: 150 Watt x 2 : 300 Watt
Chamber Temperature :
-1st Chamber : 600 – 800°C
-2nd Chamber : 800- 1000°C
Chamber Pressure : Negatif (Under Atmosferic Pressure)

Exaust Stack :
-Diameter : 450mm (1st Stack), Ø200 mm (2nd Stack)
-Height : ±8 m.from ground level
-Sampling Port Ø3”
-Coating : High Temp.Paint

Insulation and Refractory Construction Materials :
-Fire Brick : Fire Brick SK 34
-Castable : CAJ-14
-Ceramic Fibre, 128 kg/m³
-Rockwool,60 kg/m³
-Glaswool, 20 kg/m³
-Bottom : Insulating Brick

Shell & Structure Material Chamber :
-Shell Plate thickness 3 mm ,Mild Steel
-Joint Flange thickness 10 mm
-Burner Port thickness 6 mm
-Plenum Plate thickness 3 mm
-Structure UNP 80 & UNP 50
-Lifter thickness 12 mm
-Coating : Epoxy Paint

FDF Blower : Sentrifugal 3″, 370 Watt , 3000 rpm, 1 unit

Diesel Oil Fuel Consumption : average15 liter / hour

Fuel Tank :
-Tank Capacity 200 ltr
-Material Tank : Mild Steel plate t. 4 mm
-Level Control
-Drain Port

Water Scrubber : Pump, Piping with Water Tank
Maximum Capacity 190 liter/min
Electricity 220 Volt, 50 Hz, 1 Phase, 370 Watt

Power Requirement : 1,2 kW / 220 Volt / 1phase / 50Hz

Control System :
-ELC
-Temperature Control : Digital
-Thermocouple : Type – K.
-Limit Switch

Ash : 5 – 10 % waste weight
Ash Discharging : Manual
Feeding System : Manual
Warranty Term : Six month ( Service)
Operator Requirement : 1 Person
Area Requirement : 3.8 x 4.8 m

Emission Quality According to Government Regulation for the
following :
-Smokeless
-CO < 100 mg/Nm3
-NO2 < 300 mg/Nm3
-Opacity < 10%


Incinerator Cap.20 kg/Batch
Double Burner with Scrubber (Approx 180 kg/hari atau Lebih)

Jual Incinerator MKV03DB R 195x300 - Double Burner IncineratorJual Incinerator MKV04DB R 136x300 - Double Burner Incinerator

Spesifikasi :
Incinerator Cap.20 kg/Batch, Cerobong 8 meter
Incinerator Cap.20 kg/Batch, Cerobong 14 meter
Type of Waste : Bulk Density :± 0.1 – 0.15 kg/m³
Incinerator Type : Domesti Waste / Sampah Bukan B3
Incinerator Capacity : 20 kg/batch, Multiple Chamber
Operation Time : 8 hour/day

Chamber Volume :
-1st Chamber : 0.5 m³
-Mixing Room : 0.1 m³
-Second Chamber : 0.2 m³
Incinerator Dimension (Outter) : L:150 X W:120 X H:160 cm

Burner :
-1st Burner : 5 – 10 liter / hour, Light Oil Burner, Qty : 1 unit
-2nd Burner : 5 –10 liter / hour, Light Oil Burner, Qty : 1 unit
Motor 220V / 50 Hz/ 1 Phase: 150 Watt x 2 : 300 Watt
Chamber Temperature :
-1st Chamber : 600 – 800°C
-2nd Chamber : 800- 1000°C
Chamber Pressure : Negatif (Under Atmosferic Pressure)

Exaust Stack :
-Diameter : 450mm (1st Stack/Scrubber ), Ø250 mm (2nd Stack)
-Height : ±8 m.from ground level
-Sampling Port Ø3”
-Coating : High Temp.Paint

Insulation and Refractory Construction Materials :
-Fire Brick : Fire Brick SK 34
-Castable : CAJ-14
-Ceramic Fibre, 128 kg/m³
-Rockwool,60 kg/m³
-Glaswool, 20 kg/m³
-Bottom : Insulating Brick

Shell & Structure Material Chamber :
-Shell Plate thickness 3 mm ,Mild Steel
-Joint Flange thickness 12 mm
-Burner Port thickness 6 mm
-Plenum Plate thickness 3 mm
-Structure UNP 80 & UNP 50
-Lifter thickness 12 mm
-Coating : Epoxy Paint

FDF Blower : Sentrifugal 3″, 370 Watt , 3000 rpm, 1 unit

Diesel Oil Fuel Consumption : average15 liter / hour

Fuel Tank :
-Tank Capacity 250 ltr
-Material Tank : Mild Steel plate t. 4 mm
-Level Control
-Drain Port

Water Scrubber : Pump, Piping with Water Tank
Maximum Capacity 190 liter/min
Electricity 220 Volt, 50 Hz, 1 Phase, 370 Watt

Power Requirement : 1,2 kW / 220 Volt / 1phase / 50Hz

Control System :
-ELC
-Temperature Control : Digital
-Thermocouple : Type – K.
-Limit Switch

Ash : 5 – 10 % waste weight
Ash Discharging : Manual
Feeding System : Manual
Warranty Term : Six month ( Service)
Operator Requirement : 1 Person
Area Requirement : 4 x 5 m

Emission Quality According to Government Regulation for the
following :
-Smokeless
-CO < 100 mg/Nm3
-NO2 < 300 mg/Nm3
-Opacity < 10%


Incinerator Cap.30 kg/Batch
Double Burner with Scrubber(Approx 240 kg/hari atau Lebih)

Jual Incinerator MKV03DB R 195x300 - Double Burner IncineratorJual Incinerator MKV04DB R 136x300 - Double Burner Incinerator

Spesifikasi :
Incinerator Cap.30 kg/Batch, Cerobong 10 meter
Incinerator Cap.30 kg/Batch, Cerobong 14 meter

Type of Waste : Bulk Density :± 0.1 – 0.15 kg/m³
Incinerator Type : Domesti Waste / Sampah Bukan B3
Incinerator Capacity : 30 kg/Batch, Multiple Chamber
Operation Time : 8 hour/day

Chamber Volume :
-1st Chamber : 1.0 m³
-Mixing Room : 0.1 m³
-Second Chamber : 0.2 m³
Incinerator Dimension (Outter) : L:180 X W:140 X H:160 cm

Burner :
-1st Burner : 5 – 10 liter / hour, Light Oil Burner, Qty : 1 unit
-2nd Burner : 5 –10 liter / hour, Light Oil Burner, Qty : 1 unit
Motor 220V / 50 Hz/ 1 Phase: 150 Watt x 2 : 300 Watt
Chamber Temperature :
-1st Chamber : 600 – 800°C
-2nd Chamber : 800- 1000°C
Chamber Pressure : Negatif (Under Atmosferic Pressure)

Exhaust Stack :
-Diameter : 450mm (1st Stack/Scrubber), Ø250 mm (2nd Stack)
-Height : ± 10 m.from ground level
-Sampling Port Ø3”
-Coating : High Temp.Paint

Insulation and Refractory Construction Materials :
-Fire Brick : Fire Brick SK 34
-Castable : CAJ-14
-Ceramic Fibre, 128 kg/m³
-Rockwool,60 kg/m³
-Glaswool, 20 kg/m³
-Bottom : Insulating Brick

Shell & Structure Material Chamber :
-Shell Plate thickness 3 mm ,Mild Steel
-Joint Flange thickness 12 mm
-Burner Port thickness 6 mm
-Plenum Plate thickness 3 mm
-Structure UNP 80 & UNP 50
-Lifter thickness 12 mm
-Coating : Epoxy Paint

Blower : Sentrifugal 3″, 370 Watt , 3000 rpm, Qty 2 unit
atau sentrifugal 6-12 mmAg, Capacity 14 m3/min, Qty 2 unit

Diesel Oil Fuel Consumption : average 15~20 liter / hour
Fuel Tank :
-Tank Capacity 250 ltr
-Material Tank : Mild Steel plate t. 4 mm
-Level Control
-Drain Port

Water Scrubber : Pump, Piping with Water Tank
Maximum Capacity 190 liter/min
Electricity 220 Volt, 50 Hz, 1 Phase, 370 Watt

Power Requirement : 1,5 kW / 220 Volt / 1phase / 50Hz

Control System Manual and Automatic:
-ELC
-Temperature Control : Digital
-Thermocouple : Type – K.
-Limit Switch

Ash : 5 – 10 % waste weight
Ash Discharging : Manual
Feeding System : Manual
Warranty Term : Six month ( Service)
Operator Requirement : 1 Person
Area Requirement : 4 x 5.5 m

Emission Quality According to Government Regulation for the
following :
-Smokeless
-CO < 100 mg/Nm3
-NO2 < 300 mg/Nm3
-Opacity < 10%


Incinerator Cap.50 kg/Batch (0,5m3/batch)
Double Burner with Scrubber (Approx 450 kg/hari atau Lebih )

Jual Incinerator MKV03DB R 195x300 - Double Burner IncineratorJual Incinerator MKV04DB R 136x300 - Double Burner Incinerator

Spesifikasi :
Incinerator Cap.50 kg/Batch, Cerobong 10m
Incinerator Cap.50 kg/Batch, Cerobong 14m

Incinerator Type : Domesti Waste / Sampah Bukan B3
Incinerator Capacity : 50 kg/Batch, Multiple Chamber
Operation Time : 8 hour/day

Chamber Volume :
-1st Chamber : 1.7 m³
-Mixing Room : 0.4 m³
-Second Chamber : 1.0 m³
Incinerator Dimension (Outter) : L:210 X W:150 X H:190 cm

Burner :
-1st Burner : 10 – 20 liter / hour, Light Oil Burner, Qty : 1 unit
-2nd Burner : 10 –20 liter / hour, Light Oil Burner, Qty : 1 unit
Motor 220V / 50 Hz/ 1 Phase: 250 Watt x 2 : 500 Watt
Chamber Temperature :
-1st Chamber : 600 – 800°C
-2nd Chamber : 600- 1000°C
Chamber Pressure : Negatif (Under Atmosferic Pressure)

Exhaust Stack :
-Diameter : 450mm (1st Stack /Scrubber ), Ø250 mm (2nd Stack)
-Height : ±10 m.from ground level
-Sampling Port Ø3”
-Coating : High Temp.Paint

Insulation and Refractory Construction Materials :
-Fire Brick : Fire Brick SK 34
-Castable : CAJ-14
-Ceramic Fibre, 128 kg/m³
-Rockwool,60 kg/m³
-Glaswool, 20 kg/m³
-Bottom : Insulating Brick

Shell & Structure Material Chamber :
-Shell Plate thickness 4 mm ,Mild Steel
-Joint Flange thickness 12 mm
-Burner Port thickness 8 mm
-Plenum Plate thickness 3 mm
-Structure UNP 80 & UNP 50
-Lifter thickness 12 mm
-Coating : Epoxy Paint

FDF Blower : Sentrifugal 3″&4″ , 370 & 550 Watt , 3000 rpm
atau sentrifugal 6-12 mmAg, Capacity 14 m3/min, Qty 1 unit RB1
sentrifugal 8-25 mmAg, Capacity 25 m3/min, Qty 1 unit RB2

Diesel Oil Fuel Consumption : average 20 liter / hour
Fuel Tank :
-Tank Capacity 300 ltr
-Material Tank : Mild Steel plate t. 4 mm
-Level Control
-Drain Port

Water Scrubber : Pump, Piping with Water Tank
Maximum Capacity 190 liter/min
Electricity 220 Volt, 50 Hz, 1 Phase, 370 Watt

Power Requirement : 2 kW / 220 Volt / 1phase / 50Hz

Control System :
-ELC
-Temperature Control : Digital
-Thermocouple : Type – K.
-Limit Switch

Ash : 5 – 10 % waste weight
Ash Discharging : Manual
Feeding System : Manual
Warranty Term : Six month ( Service)
Operator Requirement : 1 Person
Area Requirement : 6 x 8 m

Emission Quality According to Government Regulation for the
following :
-Smokeless
-CO < 100 mg/Nm3
-NO2 < 300 mg/Nm3
-Opacity < 10%


Incinerator Cap.75 kg/Batch
Double Burner with Scrubber (Approx 800 kg/hari atau Lebih)

Jual Incinerator MKV03DB R 195x300 - Double Burner IncineratorJual Incinerator MKV04DB R 136x300 - Double Burner Incinerator

Spesifikasi :
Incinerator Cap.75 kg/Batch, Cerobong 10 meter
Incinerator Cap.75 kg/Batch, Cerobong 14 meter

Incinerator Type : Domesti Waste / Sampah Bukan B3
Incinerator Capacity : 75 kg/Batch, Multiple Chamber
Operation Time : 8 hour/day

Chamber Volume :
-1st Chamber : 2.2 m³
-Mixing Room : 0.5 m³
-Second Chamber : 1.2 m³
Incinerator Dimension (Outter) : L:280 X W:150 X H:200 cm

Burner :
-1st Burner : 10 – 15 liter / hour, Light Oil Burner, Qty : 1 unit
-2nd Burner : 10 –20 liter / hour, Light Oil Burner, Qty : 1 unit
Motor 220V / 50 Hz/ 1 Phase: 150-250 Watt x 2 : 500 Watt
Chamber Temperature :
-1st Chamber : 600 – 800°C
-2nd Chamber : 800- 1000°C
Chamber Pressure : Negatif (Under Atmosferic Pressure)

Exhaust Stack :
-Diameter : 450mm (1st Stack/Scrubber), Ø250 mm (2nd Stack)
-Height : ±10 m.from ground level
-Sampling Port Ø3”
-Coating : High Temp.Paint

Insulation and Refractory Construction Materials :
-Fire Brick : Fire Brick SK 34
-Castable : CAJ-14
-Ceramic Fibre, 128 kg/m³
-Rockwool,60 kg/m³
-Glaswool, 20 kg/m³
-Bottom : Insulating Brick

Shell & Structure Material Chamber :
-Shell Plate thickness 4 mm ,Mild Steel
-Joint Flange thickness 12 mm
-Burner Port thickness 8 mm
-Plenum Plate thickness 3 mm
-Structure UNP 80 & UNP 50
-Lifter thickness 12 mm
-Coating : Epoxy Paint

FDF Blower : Sentrifugal 4″, 550Watt , 3000rpm : 2 unit (1100Watt)
atau sentrifugal 8-25 mmAg, Capacity 25 m3/min, Qty 2 unit RB1/RB2
Diesel Oil Fuel Consumption : average 35 liter / hour

Fuel Tank :
-Tank Capacity 400 ltr
-Material Tank : Mild Steel plate t. 4 mm
-Level Control
-Drain Port

Water Scrubber : Pump, Piping with Water Tank
Maximum Capacity 190 liter/min
Electricity 220 Volt, 50 Hz, 1 Phase, 370 Watt

Power Requirement : 2.2 kW / 380 Volt / 1phase

Control System :
-ELC
-Temperature Control : Digital
-Thermocouple : Type – K.
-Limit Switch

Ash : 5 – 10 % waste weight
Ash Discharging : Manual
Feeding System : Manual
Warranty Term : Six month ( Service)
Operator Requirement : 1 Person
Area Requirement : 6 x 9 m

Emission Quality According to Government Regulation for the
following :
-Smokeless
-CO < 100 mg/Nm3
-NO2 < 300 mg/Nm3
-Opacity < 10%


Incinerator Cap.100 kg/Hour ( 1m3/batch)
Double Burner with Scrubber (Approx 800 kg/hari atau Lebih)

Jual Incinerator MKV03DB R 195x300 - Double Burner IncineratorJual Incinerator MKV04DB R 136x300 - Double Burner Incinerator

Spesifikasi :
Incinerator Cap.100 kg/Hour, Cerobong 10m
Incinerator Cap.100 kg/Hour, Cerobong 14m

Incinerator Type : Domesti Waste / Sampah Bukan B3
Incinerator Capacity : 100 kg/Batch, Multiple Chamber
Operation Time : 8 hour/day

Chamber Volume :
-1st Chamber : 2.5 m³
-Mixing Room : 0.5 m³
-Second Chamber : 1.2 m³
Incinerator Dimension (Outter) : L:360 X W:150 X H:220 cm

Burner :
-1st Burner : 10 – 15 liter / hour, Light Oil Burner, Qty : 1 unit
-2nd Burner : 10 –20 liter / hour, Light Oil Burner, Qty : 1 unit
Motor 220V / 50 Hz/ 1 Phase: 150-250 Watt x 2 : 500 Watt
Chamber Temperature :
-1st Chamber : 600 – 800°C
-2nd Chamber : 800- 1000°C
Chamber Pressure : Negatif (Under Atmosferic Pressure)

Exhaust Stack :
-Diameter : 450mm (1st Stack/Scrubber), Ø250 mm (2nd Stack)
-Height : ±10 m.from ground level
-Sampling Port Ø3”
-Coating : High Temp.Paint

Insulation and Refractory Construction Materials :
-Fire Brick : Fire Brick SK 34
-Castable : CAJ-14
-Ceramic Fibre, 128 kg/m³
-Rockwool,60 kg/m³
-Glaswool, 20 kg/m³
-Bottom : Insulating Brick

Shell & Structure Material Chamber :
-Shell Plate thickness 4 mm ,Mild Steel
-Joint Flange thickness 12 mm
-Burner Port thickness 8 mm
-Plenum Plate thickness 3 mm
-Structure UNP 80 & UNP 50
-Lifter thickness 12 mm
-Coating : Epoxy Paint

FDF Blower : Sentrifugal 4″, 550Watt , 3000rpm : 2 unit (1100Watt)
atau sentrifugal 8-25 mmAg, Capacity 25 m3/min, Qty 2 unit RB1/RB2
Diesel Oil Fuel Consumption : average 35 liter / hour

Fuel Tank :
-Tank Capacity 500 ltr
-Material Tank : Mild Steel plate t. 4 mm
-Level Control
-Drain Port

Water Scrubber : Pump, Piping with Water Tank
Maximum Capacity 190 liter/min
Electricity 220 Volt, 50 Hz, 1 Phase, 370 Watt

Power Requirement : 2.2 kW / 380 Volt / 1phase

Control System :
-ELC
-Temperature Control : Digital
-Thermocouple : Type – K.
-Limit Switch

Ash : 5 – 10 % waste weight
Ash Discharging : Manual
Feeding System : Manual
Warranty Term : Six month ( Service)
Operator Requirement : 1 Person
Area Requirement : 6 x 9 m

Emission Quality According to Government Regulation for the
following :
-Smokeless
-CO < 100 mg/Nm3
-NO2 < 300 mg/Nm3
-Opacity < 10%

Harga Incinerator tersebut sudah termasuk ;
-Supervisi Instalasi, melakukan start Up dan Commissioning
-Garansi Spare part 6 Bulan

Harga Incinerator tersebut diatas tidak termasuk ;
-Tenaga kerja Installasi
-Bangunan Pelindung
-Biaya Mobilisasi, Demobilisasi Teknisi/Supervisor ke site
-Mobilisasi, Demobilisasi Teknisi/Supervisor dan Construction Equipment untuk installasi di lapangan
-Accomodation dan Temporary Office Facility
-Pengiriman Barang Ke lokasi
Harga belum termasuk Pengujian dari Third Party Inspection
Harga belum termasuk Ijin – Ijin seperti IMB dan lain Ijin bila perlu